Adjusting Leak Closed Dates

  1. Open the component grid and pull up the tags.

  2. Open the Tag View for each tag.

  3. Click Leaks at the top and then Closed Leaks.

  4. Open the desired closed leak.

  5. Click the pen next to the Leak Closed Date.

  6. Change the Leak Closed Date to the desired date.

Was this article helpful? If not, please submit feedback below.