Group
PPM
Type (State, Event, or ClearingState)
ClearingState
Static Columns
- LUnit
- Tag
- Type
- Subtype
- Profile
- Isolatable
Live Columns
- Days Since Leak
- Last Inspection
- PPM
- AttemptDate1
- AttemptHow1
- AttemptDate2
- AttemptHow2
- AttemptDate3
- AttemptHow3
- IsDor
Trigger Criteria
- Component is a Valve, but not a Control Valve
- Last inspection PPM is 5,000 or greater (this assumes that 5000 ppm will open a leak if there isn’t one already open)
- There is no Drill and Tap or Secondary Seal Injection Repair Attempt by Day 11 after Leak Open Date